Date Topic Assignments
Sep. 2, 4 Overview of software engineering
Sep. 7 No class—Labor Day
Sep. 9, 11 Software processes and Quality management
Start of Project 1—Waterfall
Sep. 14, 16, 18 Requirements gathering SRS
Sep. 21, 23, 25 Design SDD (Draft)
Sep. 28, 30, Oct. 2 Design (continued) SDD (Final), SQAP, STP
Oct. 5, 7, 9 Implementation Implementation code
Oct. 12 No class—Columbus Day
Oct. 14, 16 Testing QA report & deliverables
Oct. 19, 21 Maintenance Maintenance report & code
Oct. 23 Exam 1
Start of Project 2—Agile + Scrum
Oct. 26, 28, 30 Intro to Scrum; Sprint 1 Sprint 1 Week 1 Report
Nov. 2, 4, 6 Sprint 1 (continued) Sprint 1 Week 2 Report
Nov. 9, 11, 13 Sprint 2 Sprint 2 Week 1 Report
Nov. 16, 18, 20 Sprint 2 (continued) Sprint 2 Week 2 Report
Nov. 23, 25, 27 No class—Thanksgiving
Nov. 30, Dec. 2, 4 Sprint 3 Sprint 3 Week 1 Report
Dec. 7, 9, 11 Sprint 3 (continued) Sprint 3 Week 2 Report
Dec. 14 Final exam: 1–3pm in LSB 212